An Abbreviated List of Milestones for the RDC1, New Haven Number 32, Budd Car, While at the Danbury Railway Museum. |
| 6-95 | Donated to Danbury Railway Museum | |
| 9-95 | Exterior Restoration Begins | |
| 4-96 | First Donated Window is Installed | |
| 6-96 | Interior Restoration Begins | |
| 8-97 | Hancock Whistle is Installed | |
| 9-97 | Number One Engine is Started | |
| 6-98 | Removal of Amtrak Seats Begins | |
| 11-98 | Last Donated Window is installed | |
| 7-99 | Airbrake System is Updated to FRA Specs | |
| 3-00 | Number Two Engine is Started | |
| 4-00 | Number Two Generator is Connected | |
| 5-00 | Floor Preparation for Tiles Begins | |
| 6-00 | Number One Drive Shaft is Re-Installed | |
|
6-00 |
Mechanical Test for First Self Powered Move | |
|
7-00 |
Prep Work for Interior Paining Begins | |
|
9-00 |
Heater/A.C. Blower is Serviced | |
|
10-00 |
Interior Painting Completed | |
|
11-00 |
Debut Run for Donators and Board Members | |
|
12-00 |
A Set of Original Type Seats is Obtained | |
|
1-01 |
Seat Restoration Begins | |
|
6-01 |
Original Style Floor Tile Installation Begins | |
|
8-01 |
First New Seats are Installed | |
|
11-01 |
Major Interior Restoration is Completed |